Algonquin Gas details pipeline plans

SALEM — Documents recently filed with the federal government illuminate Algonquin Gas’ plan to build a natural gas pipeline from Beverly Harbor to the Salem Harbor Station site.

The 16-inch, 1.4-mile long pipeline will eventually bring up to 115,000 dekatherms of natural gas per day to the proposed Footprint Power plant on Fort Avenue. Algonquin anticipates having the pipeline operational by late 2015; the plant is slated to open the following June.

Known as the Salem Lateral, the proposed pipeline will begin at an underwater connection with Algonquin’s HubLine Pipeline in Beverly Harbor, then run southwest until it makes landfall near the facility that stores liquefied natural gas on Pierce Avenue in Salem.

The pipeline will then head along the edge of the facility’s property adjacent to Waite Street before crossing Collins Cove. After it makes landfall again, the line will head through David J. Beattie Park, cross Fort Avenue and Derby Street, and then enter power plant property, where it will terminate at a metering station that will also be built as part of the project.

Total construction time is estimated to be seven months, beginning next May, with working hours from 7 a.m. to 6 p.m. six days a week, according to a recent report filed with the Federal Energy Regulatory Commission by Spectra Energy, Algonquin’s parent company.

Some of the most technically demanding parts of the pipe installation will be crossing two bodies of water: Beverly Harbor and Collins Cove. In both locations, Algonquin will use a technology known as a horizontal directional drill, or HDD.

“The HDD method is a trenchless installation process by which the pipeline is installed beneath obstacles or sensitive areas utilizing equipment and techniques derived from oil well drilling technology,” Algonquin wrote in the report.

“The process commences with the boring of a pilot hole beneath the water body to the opposite bank and then enlarging the hole with one or more passes of a reamer until the hole is the necessary diameter to facilitate the pull-back (installation) of the pipeline.”

Text Only | Photo Reprints
Local News

AP Video
Raw: 2 Shells Hit Fuel Tank at Gaza Power Plant Raw: Massive Explosions From Airstrikes in Gaza Giant Ketchup Bottle Water Tower Up for Sale Easier Nuclear Construction Promises Fall Short Kerry: Humanitarian Cease-fire Efforts Continue Raw: Corruption Trial Begins for Former Va Gov. The Carbon Trap: US Exports Global Warming UN Security Council Calls for Gaza Cease-fire Traditional African Dishes Teach Healthy Eating 13 Struck by Lightning on Calif. Beach Baseball Hall of Famers Inducted Israel, Hamas Trade Fire Despite Truce in Gaza Italy's Nibali Set to Win First Tour De France Raw: Shipwrecked Concordia Completes Last Voyage Raw: Sea Turtle Hatchlings Emerge From Nest Raw: Massive Dust Storm Covers Phoenix 12-hour Cease-fire in Gaza Fighting Begins Raw: Bolivian Dancers Attempt to Break Record Raw: Israel, Palestine Supporters Rally in US Raw: Air Algerie Flight 5017 Wreckage