Wings hand-off a milestone in Danvers High project

DANVERS — The $71 million Danvers High project passed a major milestone last week as the town took possession of the newly renovated 1960s academic wing and a new three-story science wing, albeit more than two months late.

Building Inspector Richard Maloney approved the temporary certificate of occupancy on June 28, Town Manager Wayne Marquis said. While there is still some work to be done in the two new wings, the fire alarm and sprinkler systems have been inspected and are working properly, Marquis said.

The milestone means the buildings have been transferred from the contractor, Bacon Construction of East Providence, R.I., to the town to be readied for the upcoming school year. The superintendent’s office has been moved into temporary space in the academic wing, Marquis said.

The high school’s furnishings have also been moved out of the massive, three-story Dunn wing, which for the past two school years had been used as temporary swing space for the high school. Wakefield Moving and Storage Co. was hired to move furniture and other equipment out of the Dunn wing, and school staff also helped with the move.

The wing, which was built in the early 1970s, has had chronic problems with its walls, ventilation systems and windows, and has many classrooms without windows. It is slated to be demolished with a crane the week of July 16, Marquis said. Crews must remove asbestos first.

The 650-seat auditorium has not yet been finished as the contractor waits for new seats to arrive sometime this month. The stage has been built, and wall systems and sound-absorbing acoustical ceiling clouds are being installed.

Crews are now converting the high school’s Vye gym into a temporary cafeteria, as the old high school cafeteria has been converted into instructional space, and the Dunn wing cafeteria will be torn down. The second phase of the project will include the construction of a new high school office, library, lobby and cafeteria along a central corridor. A new central office will be constructed between the field house and Vye gym.

Text Only | Photo Reprints
Local News

AP Video
Texas Scientists Study Ebola Virus Smartphone Powered Paper Plane Debuts at Airshow Southern Accent Reduction Class Cancelled in TN Raw: Deadly Landslide Hits Indian Village Obama Chides House GOP for Pursuing Lawsuit New Bill Aims to Curb Sexual Assault on Campus Russia Counts Cost of New US, EU Sanctions 3Doodler Bring 3-D Printing to Your Hand Six PA Cops Indicted for Robbing Drug Dealers Britain Testing Driverless Cars on Roadways Raw: Thousands Flocking to German Crop Circle At Least 20 Chikungunya Cases in New Jersey Raw: Obama Eats Ribs in Kansas City In Virginia, the Rise of a New Space Coast Raw: Otters Enjoy Water Slides at Japan Zoo NCAA Settles Head-injury Suit, Will Change Rules Raw: Japanese Soldiers Storm Beach in Exercises Raw: Weapons Fire Hits UN School in Gaza Raw: Rocket Launches Into Space With Cargo Ship Broken Water Main Floods UCLA