DANVERS — The $71 million Danvers High project passed a major milestone last week as the town took possession of the newly renovated 1960s academic wing and a new three-story science wing, albeit more than two months late.

Building Inspector Richard Maloney approved the temporary certificate of occupancy on June 28, Town Manager Wayne Marquis said. While there is still some work to be done in the two new wings, the fire alarm and sprinkler systems have been inspected and are working properly, Marquis said.

The milestone means the buildings have been transferred from the contractor, Bacon Construction of East Providence, R.I., to the town to be readied for the upcoming school year. The superintendent’s office has been moved into temporary space in the academic wing, Marquis said.

The high school’s furnishings have also been moved out of the massive, three-story Dunn wing, which for the past two school years had been used as temporary swing space for the high school. Wakefield Moving and Storage Co. was hired to move furniture and other equipment out of the Dunn wing, and school staff also helped with the move.

The wing, which was built in the early 1970s, has had chronic problems with its walls, ventilation systems and windows, and has many classrooms without windows. It is slated to be demolished with a crane the week of July 16, Marquis said. Crews must remove asbestos first.

The 650-seat auditorium has not yet been finished as the contractor waits for new seats to arrive sometime this month. The stage has been built, and wall systems and sound-absorbing acoustical ceiling clouds are being installed.

Crews are now converting the high school’s Vye gym into a temporary cafeteria, as the old high school cafeteria has been converted into instructional space, and the Dunn wing cafeteria will be torn down. The second phase of the project will include the construction of a new high school office, library, lobby and cafeteria along a central corridor. A new central office will be constructed between the field house and Vye gym.

Text Only | Photo Reprints
Local News

AP Video
Obama Hopeful on Ukraine, Will Watch Russians Flamingo Frenzy Ahead of Zoo Construction Crew Criticized Over Handling of Ferry Disaster Agreement Reached to Calm Ukraine Tensions Raw: Pope Francis Performs Pre-easter Ritual Raw: Bulgarian Monastery Dyes 5000 Easter Eggs Diplomats Reach Deal to Ease Tensions in Ukraine U.S. Sending Nonlethal Aid to Ukraine Military Holder: Americans Stand With KC Mourners Obama Greets Wounded Warriors Malaysia Plane: Ocean Floor Images 'Very Clear' Sparks Fly With Derulo and Jordin on New Album Franco Leads Star-studded Broadway Cast Raw: Two Lucky Kids Get Ride in Popemobile Boston Bombing Survivors One Year Later Sister of Slain MIT Officer Reflects on Bombing